Walking Tour - Allston Under Construction
ABHA Organizing Team
event neighborhood
Tour Notes
Building on the success of our August walking tour, we decided to take another walk around Allston to see some buildings that are currently under construction. About 25 people, including group regulars and new faces, joined us on a sunny Halloween afternoon. See below for some notes and photos from the walk! If you missed it, sign up for our newsletter to be notified of future events.

1270 Commonwealth Avenue (“Arborline”)
- 5 stories of wood-frame construction over a 1-story concrete podium
- 206 units, 70 ground level parking spaces (.34 ratio)
- Developer: Hines/Benenson Capital Partners
- Architect: CBT
- GC: Tocci
- Project filed in 2022, approved in 2023
- Mostly finished with excavation, currently working on footings/foundation and first floor columns

25-39 Harvard Avenue (“The Ivy”, formerly “Allston Post”)
- 5 stories of wood-frame construction over a 1-story steel podium
- 170 units, 58 ground level parking spaces (.34 ratio)
- Developer: Eden Properties
- Architect: Embarc
- GC: Cranshaw
- Project filed and approved in 2023, target completion in June 2027
- Framing is complete, windows almost in, moisture barrier being applied
- Going to add street trees
- On the site of the former Allston Post Office

6 Pratt Street (“Allston Green” Building C)
- 4 stories of wood-frame construction
- 68 units, no parking
- Developer: LBC
- Architect: PCA
- GC: Reycon
- Project filed in 2019, approved in 2020
- Currently finishing framing, part of a 3-building project

120 Braintree Street (“Riva Residences”)
- 4 stories of wood-frame construction over a 1-story steel podium
- 32 condo units, 31 ground level parking spaces (.97 ratio)
- Developer: Zanzibar Capital
- Architect: MFDS
- GC: Drack
- Project originally filed by the owner of the cab company that used to operate on the site
- Filed in 2021, approved in 2021, reapproved in 2025 after a change in ownership and parking design
- Finished podium, working on framing

95 Everett Street
- 5 stories of wood-frame construction over a 2-story cast-in-place concrete podium
- 88 income-restricted units, no parking
- Developer: Pennrose
- Architect: DiMella Shaffer
- GC: Dellbrook
- Part of a larger plan to redevelop 119 Braintree Street
- First approved in 2020, approved in 2023, target completion in Summer 2027
- Done with framing, currenting wrapping moisture barrier and installing light gauge steel studs in the duplex units

250 Everett Street (“Modera Allston”)
- 5 stories of wood-frame construction over a 1-story steel podium
- 240 units, 117 underground parking spaces (.49 ratio)
- Developer: Mill Creek
- Architect: CUBE 3
- GC: Mill Creek
- Filed in 2024, approved in 2025
- Foundation concrete poured, parts of ground floor poured, working on columns and utilities